Title: Exact algorithm for minimizing the sum of total late work and maximum late work problem
Authors: Adawiyah A. Mahmood Al-Nuaimy
Tariq S. Abdul-Razaq
Keywords: Late work criterion,branch and bound algorithm, bi-criteria scheduling
Issue Date: 2014
Publisher: university of Diyala
Abstract: This paper presents a branch and bound (BAB) algorithm for minimizing the sum of total late work and maximum late work problem within the single machine context. Late work is the amount of work executed after a given due date. Branch and bound (BAB) is proposed, two heuristic methods are used to find an upper bound. This BAB proposes a lower bound based on the decomposition property of the bi-criteria problem. Based on results of computational experiments, conclusions are formulated on the efficiency of the BAB algorithm.
URI: http://148.72.244.84:8080/xmlui/handle/xmlui/8558
ISSN: 2222-8373
Appears in Collections:مجلة ديالى للعلوم الاكاديمية / Academic Science Journal (Acad. Sci. J.)

Files in This Item:
File Description SizeFormat 
h3.pdf354.99 kBAdobe PDFView/Open


Items in DSpace are protected by copyright, with all rights reserved, unless otherwise indicated.